Analysis of Time and Cost Efficiency of Conventional Methods and Steel Decks in Highway Bridge Deck Slab Construction
DOI:
https://doi.org/10.65310/0gqrfs14Keywords:
Steel Deck, Cast In Situ, Deck Slab, Cost Efficiency, Time Efficiency.Abstract
This study investigates the comparative efficiency of conventional cast-in-situ and steel deck methods for bridge deck slab construction in the Kapuk–Teluknaga–Rajeg Toll Road Project Phase I, Banten Province, Indonesia. The research applies a field-based empirical case study design with a quantitative approach, using primary data from site observations and structured interviews, and secondary data from shop drawings, project specifications, and cost documents. Cost estimation was conducted using unit price-based analysis following AHSP standards regulated by Permen PUPR No. 28/PRT/M/2016, while construction duration was calculated based on actual productivity and activity sequencing. The results indicate that the conventional method required 17 working days with a total cost of Rp 592,003,970, whereas the steel deck method required only 8 working days with a total cost of Rp 553,984,460. These findings demonstrate that steel deck provides a 52.94% reduction in construction time and a 6.42% cost saving. The study further shows that steel deck shifts project cost structure from labor-intensive operations to controlled material-based execution, improving schedule reliability and construction productivity.
Downloads
References
Akbar, M., Aminullah, A., & Awaludin, A. (2025). Efektifitas Metode Ssi Covariance Dalam Sistem Pemantauan Kesehatan Struktur (Shms) Jembatan Box Girder Bentang 40 Meter. Teras Jurnal: Jurnal Teknik Sipil, 15(2), 457-468. Https://Doi.Org/10.29103/Tj.V15i2.1293
Al-Sabah, A., Al-Hussein, M., & Zayed, T. (2023). Construction Productivity Enhancement Using Composite Steel–Concrete Systems. Journal Of Construction Engineering And Management, 149(3), 04022145. Https://Doi.Org/10.1061/(Asce)Co.1943-7862.0002456
Andre, Y. H. (2023, May). Perubahan Metode Plat Pracetak Menjadi Steel Deck Dan Pengadaan Besi Sesuai Cutting List Untuk Efisiensi Biaya Pada Proyek Kapb Seksi 3b. In Seminar Nasional Insinyur Profesional (Snip) (Vol. 3, No. 1). Https://Doi.Org/10.23960/Snip.V3i1.364
Christian, M., & Kushartomo, W. (2023). Analisis Perbandingan Efektifitas Beton Pelat Lantai Dengan Metode Bondek Dan Konvensional. Jmts: Jurnal Mitra Teknik Sipil, 627-634. Https://Doi.Org/10.24912/Jmts.V6i3.23016
Desrita, D., Ginting, T. P., Ginting, R., & Gultom, A. (2024). Penerapan Manajemen Konstruksi Pada Proyek Pembangunan Jembatan Idano Sibolou Afulu–Batas Nias Barat. Jurnal Ilmiah Teknik Sipil, 13(1), 108-119. Http://Dx.Doi.Org/10.46930/Tekniksipil.V13i1.3636
Dewi, I. C., Priyono, P., & Yanuar, S. F. (2025). Pemodelan Lantai Kendaraan Pada Jembatan Rangka Terbuka Bentang Panjang Dengan Mengabaikan Efek P-Δ Pada Batang Tepi Atas. Media Konstruksi, 10(2), 232-241. Https://Doi.Org/10.33772/Jmk.V10i2.106
Fatoni, A., Huda, M., & Priyoto, P. (2024). Analisis Perbandingan Biaya Dan Waktu Pelaksanaan Pelat Lantai Beton Panel Dan Beton Konvensional (Studi Kasus Proyek Pembangunan Smp Islam Terpadu Al-Irsyad Al-Islamiyah Kabupaten Pamekasan). Jurnal Spesialis Teknik Sipil (Jspts), 5(1), 1-14. Https://Doi.Org/10.30996/Jspts.V5i1.10730
Harefa, M. B., Rizalitaher, A. S., & Harefa, A. (2023). Perencanaan Struktur Atas (Upper Structure) Jembatan Bilal. Juitech: Jurnal Ilmiah Fakultas Teknik Universitas Quality, 7(1), 37-45. Http://Dx.Doi.Org/10.36764/Ju.V7i1.1066
Hwang, B. G., Shan, M., & Supa’at, N. N. B. (2021). Factors Affecting Productivity In Construction Projects: A Systematic Review. Engineering, Construction And Architectural Management, 28(4), 1115–1133. Https://Doi.Org/10.1108/Ecam-08-2019-0451
Kementerian Pekerjaan Umum Dan Perumahan Rakyat. (2016). Peraturan Menteri Pupr Nomor 28/Prt/M/2016 Tentang Analisis Harga Satuan Pekerjaan Bidang Pekerjaan Umum.
Kementerian Pekerjaan Umum Dan Perumahan Rakyat. (2023). Laporan Kinerja Pembangunan Jalan Tol Tahun 2023.
Kim, J., & Lee, H. (2020). Comparative Performance Of Composite Deck Slab Systems In Accelerated Bridge Construction. Structures, 28, 2103–2114. Https://Doi.Org/10.1016/J.Istruc.2020.10.015
Nguyen, T. T., Kim, S., & Park, J. (2022). Performance Evaluation Of Composite Steel Deck Slabs Under Construction Loads. Journal Of Structural Engineering, 148(7), 04022098. Https://Doi.Org/10.1061/(Asce)St.1943-541x.0003345
Piter, M. A., & Sucita, I. K. (2024). Perbandingan Analisis Quantity Takeoff Berbasis Bim Dengan Metode Konvensional Pada Pekerjaan Struktur Jembatan Underpass. Civeng: Jurnal Teknik Sipil Dan Lingkungan, 5(2), 83-90. Https://Doi.Org/10.30595/Civeng.V5i2.19126
Prabaswara, A. B., & Nurdianto, R. (2024). Analisis Perbandingan Plat Beton Konvensional Dan Plat Beton Bondek. Jitsi: Jurnal Ilmiah Teknik Sipil, 4(2), 107-115. Https://Doi.Org/10.36423/Jitsi.V4i2.1987
Pradhan, R. P., Arvin, M. B., & Hall, J. H. (2020). Infrastructure And Economic Growth: The Role Of Transport Infrastructure. Economic Modelling, 93, 1–11. Https://Doi.Org/10.1016/J.Econmod.2020.02.005
Prasetyo, B. N., & Manurung, E. H. (2026). Evaluasi Efisiensi Penggunaan Beton Bertulang Pada Struktur Jembatan. Sinergi: Jurnal Riset Ilmiah, 3(1), 208-218. Https://Doi.Org/10.62335/Sinergi.V3i1.2238
Riyadi, I., Handayani, E., & Dony, W. (2022). Analisa Perbandingan Sistem Pelat Konvensional Dengan Sistem Precast Half Slab Dalam Segi Waktu Dan Biaya. Jurnal Civronlit Unbari, 7(2), 63-69. Http://Dx.Doi.Org/10.33087/Civronlit.V7i2.100
Sasmito, A. (2023). Analisis Risiko Pekerjaan Fire Fighting System Pada Proyek Sktt 150 Kv Di Jembatan Suramadu Dengan Metode Hazard Identification Ris Assessmentand Risk Control (Hirarc). Jurnal Syntax Admiration, 4(8), 1051-1070. Https://Doi.Org/10.46799/Jsa.V4i8.683
Sawaluddin, S., Kadir, A., & Edwin, R. S. (2024). Analisis Penerapan Value Engineering Pada Konstruksi Lantai Jembatan Cable Stayed. Siklus: Jurnal Teknik Sipil, 10(1), 66-79. Https://Doi.Org/10.31849/Siklus.V10i1.19189
Susila, H., & Sungkono, K. K. D. (2025). Analisis Biaya Dan Waktu Pekerjaan Pelat Lantai Beton Konvensional Dan Fiber Board Pada Bangunan Baja. Journal Of Civil Engineering And Infrastructure Technology, 4(1), 27-36. Https://Doi.Org/10.36728/Jceit.V4i1.5014
Sweis, G., Sweis, R., & Abu Hammad, A. (2020). Time–Cost Trade-Off Analysis In Construction Projects. International Journal Of Construction Management, 20(7), 653–663. Https://Doi.Org/10.1080/15623599.2018.1484867
Yin, R. K. (2021). Case Study Research And Applications: Design And Methods (6th Ed.). Sage Publications.
Yulianto, Y., Azhar, M., Naibaho, P. R. T., & Sembiring, K. (2026). Perbandingan Biaya Dan Waktu Pelaksanaan Deck On Pile Dengan Cakar Ayam Modifikasi Pada Pembangunan Dermaga Jakarta International Container Terminal 2. Jurnal Komposit: Jurnal Ilmu-Ilmu Teknik Sipil, 10(1), 103-112. Https://Doi.Org/10.32832/Komposit.V10i1.20507
Downloads
Published
Issue
Section
License
Copyright (c) 2026 Kodrat Insany Taqwim (Author)

This work is licensed under a Creative Commons Attribution 4.0 International License.



















