Evaluasi Produktivitas Tenaga Kerja Konstruksi Menggunakan Metode Work Sampling pada Pekerjaan Struktur Beton

Penulis

  • Riyan Putra Pratama Universitas Ratu Samban Penulis
  • Rezi Munizar Universitas Ratu Samban Penulis

DOI:

https://doi.org/10.65310/6gv8md86

Kata Kunci:

Idle Time, Labor Productivity, Labor Utilization Rate, Reinforced Concrete Structure, Work Sampling.

Abstrak

Labor productivity is a critical factor influencing the success of construction projects in terms of cost, quality, and schedule performance. This study aimed to evaluate labor productivity in reinforced concrete structural works, including reinforcement, formwork, and concreting, using the Work Sampling method. A quantitative observational approach was employed through random observations to classify workers' activities into three categories: Effective Work, Essential Contributory Work, and Idle Time. The observation data were analyzed using the Labor Utilization Rate (LUR) indicator to measure the efficiency of labor time utilization. The results showed that the project's average LUR was 55.50%, indicating satisfactory labor productivity as it exceeded the industry benchmark of 50%. Reinforcement work achieved the highest LUR of 62.10%, while concreting recorded the lowest LUR of 47.10% due to high Idle Time caused by delays in ready-mix concrete delivery, concrete pump interruptions, and inefficient material layout. These findings provide a basis for improving logistics management and work coordination to enhance productivity in reinforced concrete construction projects.

Unduhan

Data unduhan tidak tersedia.

Referensi

Anugrah, Y. C. (2025). Penggunaan Metode Work Sampling dan Metode Relative Importance Index (RII) untuk Menganalisis Produktivitas Tenaga Kerja Pembetonan Retaining Wall (Studi Kasus: Pembangunan RS EMC Sentul). In Prosiding Seminar Nasional Teknik Sipil (Vol. 7, No. 2, pp. 1362-1369). https://prosiding.pnj.ac.id/index.php/snts/article/view/4968

Dharsono, M. S., & Hindun, S. (2024). Analysis of Labor Productivity of Beam and Floor Plate Work with Work Sampling Method. Jurnal Pensil: Pendidikan Teknik Sipil, 13(3), 287-298. https://doi.org/10.21009/jpensil.v13i3.44934

Hutagaol, K., Wahyudi, S. I., & Adi, H. P. (2026). Model Implementasi Koefisien Produktivitas Tenaga Kerja pada Pekerjaan Struktur Kolom, Balok, dan Plat Berdasarkan Analisis Harga Satuan Pekerjaan (AHSP) PUPR Studi Kasus Gedung Nalanda. RESWARA: Jurnal Riset Ilmu Teknik, 4(3), 217-227. https://doi.org/10.70716/reswara.v4i3.469

Iskandar, D. N., & Pranata, G. (2024). Analisis Produktivitas Tenaga Kerja Pada Pengerjaan Kolom di Proyek DNL. JMTS: Jurnal Mitra Teknik Sipil, 321-328. https://doi.org/10.24912/jmts.v7i1.26716

Latuihamallo, Y. L., Rehatta, G. B., & Gaspersz, W. (2023). Analisis Produktivitas Tenaga Kerja dengan Metode Work Sampling pada Proyek Rehabilitasi dan Renovasi Laboratorium IAIN Ambon. Journal Agregate, 2(2), 230-239. https://doi.org/10.31959/ja.v2i2.1854

Lee, T. Y., Ahmad, F., & Sarijari, M. A. (2024). Activity Sampling in The Construction Industry: A Review and Research Agenda. International Journal Of Productivity And Performance Management, 73(5), 1479-1501. https://doi.org/10.1108/IJPPM-10-2022-0507

Lumbangaol, P., Saragi, Y., & Purba, L. H. (2024). Produktivitas Pekerja Proyek Konstruksi dan Faktor yang Mempengaruhi. Jurnal Darma Agung, 32(4), 75-84. http://dx.doi.org/10.46930/ojsuda.v32i4.4620

Mirnayani, M., & Prakoso, S. H. (2024). Analisis Produktivitas Tenaga Kerja Proyek Konstruksi Pekerjaan Shear Wall dengan Metode Work Sampling. Go Infotech: Jurnal Ilmiah STMIK AUB, 30(1), 96-104. https://doi.org/10.36309/goi.v30i1.264

Nicholas, & Arumsari, P. (2025, December). Analysis of Labour Productivity in Concrete Element Structure in High Rise Building (Case Study: Nafiri Discipleship Church). In IOP Conference Series: Earth and Environmental Science (Vol. 1564, No. 1, p. 012048). IOP Publishing. https://doi.org/10.1088/1755-1315/1564/1/012048

Oglesby, C. H., Parker, H. W., & Howell, G. A. (1989). Productivity Improvement in Construction. New York: McGraw-Hill.

Putri, W. N. A., Usman, K., & Siregar, A. M. R. (2025). Analisis Faktor yang Mempengaruhi Produktivitas Tenaga Kerja dengan Fuzzy AHP pada Proyek Bantalan Beton Divre IV Tanjungkarang. Jurnal Komposit: Jurnal Ilmu-ilmu Teknik Sipil, 9(1), 161-171. https://doi.org/10.32832/komposit.v9i1.17563

Romadhon, F., Kader, I., & Sudiarta, I. K. (2023). Evaluasi Efektivitas Tenaga Kerja Pekerjaan Struktur Lantai 1 Pada Proyek Pembangunan Gedung Kantor PT. Tunas Jaya Sanur Group (Doctoral dissertation, Politeknik Negeri Bali). https://repository.pnb.ac.id/id/eprint/9489/

Santiana, I. M. A., Sujahtra, I. W., Tapayasa, I. M., Wibawa, I. G. S., & Sudiasa, I. W. (2024). Analysis of Labor Productivity in Reinforced Concrete Structures Using Time Study Methods. International Research Journal of Engineering, IT and Scientific Research, 10(3), 38-48. https://doi.org/10.21744/irjeis.v10n3.2434

Santy, T., & Mara, J. (2023). Analisis Produktivitas Tenaga Kerja Proyek Gedung Apartemen Bandaraya. Paulus Civil Engineering Journal, 5(2), 284-293. https://doi.org/10.52722/88kaew17

SAPUTRA, N. (2025). Analisis Produktivitas Pekerja pada Proyek Konstruksi dengan Metode Productivity Delay Model (Doctoral dissertation, Universitas Islam Sultan Agung). https://repository.unissula.ac.id/44234/

Sari, T. P., Kuryanto, T. D., & Ahmad, H. H. (2026). Analisis Produktivitas Pekerja Menggunakan Metode Work Sampling Gedung Toserba Kds Situbondo. Jurnal Media Akademik (JMA), 4(7). https://doi.org/10.62281/v18vba64

Soeharto, Iman. (1995). Manajemen Proyek: Dari Konseptual Sampai Operasional. Jakarta: Erlangga.

The Business Roundtable. (1982). Improving Construction Productivity on Site. Report A-1. New York.

Waldemar, W., Kartika, N., & Robial, S. M. (2022). Productivity Analysis Of Floor Heroning Workers Using Work Sampling Method. Jurnal Pensil: Pendidikan Teknik Sipil, 11(2), 162-170. https://doi.org/10.21009/jpensil.v11i2.25474

Wulfram I. Ervianto. (2005). Manajemen Proyek Konstruksi. Yogyakarta: Andi.